Brightstar Resources Says Development Activities at Western Australia Project on Schedule

MT Newswires Live
5 hours ago

Brightstar Resources (ASX:BTR) said construction and development activities at its Goldfields project in Western Australia are on schedule, with first gold on track for June 2027, according to a Tuesday filing with the Australian bourse.

A final major concrete pour in the primary crusher area is now complete, and the first structural steel erection has started at the surge bin, per the filing.

Earthworks and civil concrete works have started at the LNG power station, while civil works are progressing in the gold recovery and elution areas.

The company said site establishment works have also started at the Lord Byron open pit, alongside mining development activities to prepare the site for non-process infrastructure ahead of mining mobilization targeted for early in the March quarter next year.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.