Grange Resources Approves Final Investment Decision for Tasmania Project, NPV at AU$357 Million; Shares Up 11%

MT Newswires Live
Oct 14

Grange Resources (ASX:GRR) said its board made a final investment decision for the North Pit Underground Project at its Savage River Iron Ore Pellet Operations in northern Tasmania, according to a Wednesday Australian bourse filing.

The company said base-case economics, at an iron ore price of $90 per tonne for 62% iron fines, show a project net present value of AU$357 million, at 8.3% real after tax, and an internal rate of return of 43%.

The company expects underground mining to begin in the first quarter of 2027.

The project extends production and pellet supply continuity to 2035, with potential to extend beyond 2040 under a future block cave development at Savage River or alternative open-pit options, the filing said.

The company said a staged development approach preserves the option for a block cave, with a decision to be made at a future date.

The company's shares rose 11% in recent Wednesday trade but earlier hit a 52-week low.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.